Home - Phase Overview | ||
Project Planning Phase |
The purpose is threefold.
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
The timing will depend on the size of the project. For a simple project, the whole exercise may only take two or three days. For a major project, it may last a number of weeks. Many of the activities can be worked on concurrently. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
There is always pressure to get things started on the project rather than plan. "Ready", "Fire", "Aim". The more effort that goes into planning the more successful the project will be. First activity is to justify the project with a Project Charter. If the project has already been approved, there may be less effort required in this area. The level of maturity of the organisation will determine the effort required for quantifying benefits and costs. A less mature organisation will not track benefits or costs effectively so the effort will probably be wasted to a certain extent. That is not to say there shouldn't be a solid business case. It is to say the organisation may well ignore it anyway. In the case where the project absolutely needs to be done - for example where it is to meet legislative requirements - the cost and benefits may be immaterial. The schedule is something that must be done. You need to set an expectation as to when the project will be completed, and the resources required. This cannot happen without a schedule. You will be unable to track progress without a schedule so it is an essential. The Project Management Plan is about how you will manage the project. As an organisation builds it's project infrastructure, many of the components will be reusable from project to project. For example there will be a standard issue log or risk log. These can significantly reduce the effort required in the planning step. Simply use standard tools and mention that fact in the PMP. The critical parts of the PMP that will have a big impact on the success are those relating to resources. Resources must be agreed before you proceed. Equally important is to have everyone understand what the responsibilities of each resource will be. The two go hand in hand. You need a person to undertake a set of duties so the person assigned must be capable of undertaking those duties. It also determines the time they will need to allocate. The communication plan is another "must do". Poor communication is a major risk on any project so it should be given the attention it requires during this planning stage. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
There is a logical sequence to the activities.
Some activities can be worked on concurrently. For example we can concurrently develop processes for change control, risks, procurement and budget control. In fact as you build up expertise, these should be "off the shelf" processes that have been used in other projects. Similarly roles and responsibilities can be largely "off the shelf". |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||