Configure the system, carry out any customisation, prepare and convert data and test the solution. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
The
timing cannot be finalised until the data preparation, configuration
and customisation is scoped and scheduled. The initial plan is
likely to be a high level estimate, developed with the input of
the vendor. It will usually be clear what has to be done, but
the resourcing of the work, and scheduling may cause the plan
to be modified. If this is so, it should be referred to the Sponsor
for agreement.
When carrying out the planning, you might estimate one task to clean up the database will take X weeks. When you get down to the activity "Identify Data Conversion Requirements" you will do more detailed planning to the level below:
At the planning stage you may have allowed X weeks to clean up data. Once you do the investigation, and put together a final plan, it may be 2X. When you look at resource availability, the elapsed time may become 3X. If this is going to change the overall time for the phase, you should discuss with the Sponsor and Steering Committee. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
If the work involved is well beyond the expectations of the company, you should look at phasing the implementation. Perhaps some work can be done after a partial implementation. For example, very often reporting can wait a few weeks or even a few months after implementation. The phase will also be constrained (and constrain) the Business Process Phase. The two need to work in parallel and often resources are swapped between each team. If one is moving ahead of the other, consider transferring resources such as Business Analysts between teams. The biggest surprises are often in data conversion. A trial conversion should happen as quickly as possible and not wait until everything is cleaned up. No point in getting to the end of the work before finding more unknowns. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
The goal of this phase is to achieve the following outcomes.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||